Construction Update 18 July - Commencement of Structure

Structure of the Rosenthal Project is now underway, with the team completing 48 pad footings as well as commencing footings to the lifts and stairwells in the southern portion of the site.

A quick and fun construction crash course: A footing is a structure upon which a building sits that transfers loads from the weight from walls and columns via footings to the earth.

Whilst we wrap up excavation in the northern portion of the site (which is expected in late August), a concrete placement boom will be commissioned. This will enable the team to commence concrete placement of the slab on ground to the southern areas of the site.