Construction Update- 2 November 2018

Since our previous web article, the project’s excavation works have wrapped up and structure well progressed.
The project is running smoothly on programme and on budget with over 50 % of the southern portion structure constructed.

Status of the Structure:

Basement Level 3- 50% of the slab on ground and verticals (Walls, Columns, Lift and Stair shafts, Ramps) complete
Basement Level 2- 50% of the suspended slab and verticals (Walls, Columns, Lift and Stair shafts, Ramps) complete
Basement Level 1- 50% of the suspended slab and verticals (Walls, Columns, Lift and Stair shafts, Ramps) complete
Basement Level 0- Currently installing formwork and reinforcement to the suspended slab

Foundations to the northern portion of the project have commenced, with the area being prepared for the slab on ground concrete works.